KEY FEATURES
Capacity of Storage 2.50 MMT (18.37 MM bbl)
Approved cost of construction Rs. 1693 crores (*273 USD Million)
Zero date for construction May, 2010
Land area in Acres 179.21
No of compartments 4
Capacity of compartments in MMT
1 2 3 4
0.625 0.625 0.625 0.625
Contractor for UG works HCC & SKEC-KCT JV
Contractor for AG works Linde Engg
Contractor for laying of pipeline IL & FS
Commissioned in December 2018

*1 USD equal to Rs.62/-